Two companies will realize part 1 and 2 of the express route between Craiova and Pitesti



The Road Company indicates that Tierra Scavi (Italy) will realize the 17.7 km long stretch, which means it will receive 358.179 million lei without VAT (76 million euros).

Part 2, which is divided into two lots, will be developed by the association SA & PE Construct SRL-Spedition UMB SRL-Tehnostrade SRL-Consitrans SRL (Romania). Party 1 of Section 2 has a length of 18.5 km and 661.452 million slate was offered excluding VAT (141 million euro), and plot 2 of the same section, which is 23.35 km long, will be made by the same consortium, with 795.189 million slate excluding VAT (168 million euros).

"Today, 1 October 2018, CNAIR has nominated the winners of the design and implementation contracts for sections 1 and 2 of the Craiova-Pitesti express road", the company announces.

CNAIR announces that Section 1 has a length of 17.7 km (km 0 + 000 – km 17 + 700) and that the point of departure is the detachment of the northern ring road of the municipality of Craiova and lastly the border of Dolj County with Olt. "This section crosses the administrative areas of the following places: Craiova, Gherceşti, Pieleşti and Robăneşti," the company said.

"The part 2 has a length of 39.85 km (km 17 + 700 – km 57 + 550), it has a starting point between the counties Dolj and Olt and as last point after Slatina, at the intersection with DN 65. It is crossed the administrative areas of the following places: Bals, Bârza, Piatra Olt, Slătioara, Ulmi, Slatina and Valea Mare Part 2 is divided into 2 lots – lot 1 with a length of 18.5 (km 17 + 700 – km 36 + 200) and plot 2 with a length of 21.35 (km 36 + 200 – km 57 + 550) CNAIR announced.

According to the company, the execution of plot 1 will lead to the decongestation of traffic from the area of ​​Bals, and through the lot 2, the decongestion of traffic from the Slatina site, by diverting the traffic outside the places.

"According to the contract provisions, the duration of these contracts has been 36 months, 12 months for the design activity and 24 months for the execution of the works and a guarantee period for the 7-year work," says the National Road Company. "The signing of the three contracts can only be started after the expiry of the 10-day appeal period after sending the results of the procedure.If there is an appeal against the result of the procedure, CNAIR SA awaits their settlement for the signing process. of the contract, "CNAIR noted.

At the moment, the public procurement procedures for the design and execution services of parcels 3 and 4 of the express road Craiova-Pitesti are being processed by the Supreme Court of Cassation and Justice.

Present at Craiova, during a visit to Craiova's Aircraft Factory, PM Viorica Dăncilă stated that "the design and execution contracts for the motorway under the Craiova-Piteşti motorway are laid down, paragraphs 1 and 2. Term is 36 months and the warranty period is 7 years ", and the Minister of Transport, he also said that the two companies that won the contracts" have guarantees that these works will be carried out on time ".