Derailed construction train at Ebikon: Railway again reasonable – News: standard



Almost 48 hours after an accident during construction work, the Luzern-Zurich railway line at Ebikon LU was released at 2 pm on Tuesday. The trains could return to normal, said a spokesman for the SBB.

On Sunday at 3 pm a train had jumped out of the rails between Luzern and the suburb of Ebikon in the area of ​​track renewal. The railway system was so badly damaged that the maintenance work dragged in on Tuesday.

The train had to be lifted extensively with a rail crane. Moreover, the damage was greater than originally assumed. So extra gravel had to be added on Tuesday.

Follow the extension until October

Train passengers between Lucerne and Zug and Zurich had to accept longer traveling times during the interruption. The Interregio trains fell on places or were diverted via Olten. In addition, the S-Bahn S1 between Luzern and Ebikon were replaced by buses.

The construction work, which was carried out during the weekend and during which the accident occurred, is part of an extensive job renewal between Luzern and Ebikon over a length of 1860 meters. The work lasts from 1 July to 17 October and usually takes place late or & # 39; in the evening.

Damage greater than expected

Because the train jumped out of the rails at an unfavorable point, the blocking is prolonged. On the one hand, because the train had to be lifted with a rail crane. On the other hand, because the damage was greater than initially assumed, as the SBB spokesman said further.

The construction work at the weekend is part of an extensive track renewal between Luzern and Ebikon over a length of 1860 meters, with the SBB a total of about 3200 tons of gravel. The work lasts from 1 July to 17 October and usually takes place late or & # 39; in the evening.

(Oli / SDA)